强夯施工地基的锤重、落距、夯击点布置及各个夯击点的夯击次数必须符合设计要求。
The hammer weight, drop distance, arrangement of tamping points and
tamping times of each tamping point must meet the design requirements.
强夯施工的夯击遍数和两遍之间的间隔时间必须符合设计要求或施工规范的规定。
The number of times of tamping and the interval between the two times
must meet the design requirements or construction specifications.
2.基本项目
2. Basic Projects
强夯后,基坑(槽)表面不得有松土。
After dynamic compaction, no loosening of soil shall be allowed on the surface of the foundation pit (groove).
3.允许偏差项目
3. Allowable deviation items