强夯施工阶段准备工作有哪些

网址:www.qianghangshigong.com.cn  2019-05-09  作者:admin    阅读:

1)检查和督促施工单位健全质量及安全保证措施
1) Inspection and supervision of construction units to improve quality and safety assurance measures
整个强夯施工过程中安全是最重要的,强夯施工承包单位都应有项目经理全面负责,并设施工员、质量员和资料员、安全员,在施工现场进行全过程质量管理和质量控制。建立施工工序的自检验收制度。
Safety is the most important in the whole dynamic compaction construction process. The project manager should be fully responsible for the dynamic compaction construction contractors. Facilities, quality personnel, information personnel and safety personnel should carry out the whole process quality management and quality control at the construction site. Establish a self-inspection collection system for construction process.
2)对施工队伍及人员控制
2) Control of construction team and personnel
审查承包单位施工队伍及人员的技术资质与条件是否符合要求,项目监理部审查认可后,方可上岗施工;对不合格人员,项目监理部有权要求承包单位予以撤换。
To examine whether the technical qualifications and conditions of the construction team and personnel of the contractor are in conformity with the requirements, the project supervision department shall not take up the post until it has examined and approved the qualifications; to the unqualified personnel, the project supervision department shall have the right to request the contractor to replace them.
3)施工准备的检验和监理
3) Inspection and supervision of construction preparation
强夯施工准备工作的检查是预控的重要环节。对于分部工程的开工,监理工程师要着重从工程质量保证角度逐项审查。对于不具备开工条件者,有权要求施工单位暂缓开工,直至达到开工条件为止。
The inspection of dynamic compaction construction preparation is an important part of pre-control. For the start-up of a branch project, the supervisory engineer should focus on examining each item from the point of view of project quality assurance. For those who do not have the conditions for start-up, they have the right to request the construction unit to suspend the start-up until the conditions for start-up are met.